CTG-owned Changlongshan pumped storage power station hoists first stator

from:China Three Gorges Corporationdate:2020-10-07

CTG-owned Changlongshan pumped storage power station hoists first stator-1

Changlongshan pumped storage power station, built and owned by China Three Gorges Corporation (CTG), announced that it has hoisted the No. 1 power unit's stator on September 26, the heaviest component it has hoisted since the project started.

The hoisting of the stator marks that the No.1 power unit’s general assembly is now entering the final phase, which is expected to be finished within this year before rotor hoisting and hydrocoupling.

The installation of No.1 power generator will lay a solid foundation for its planned commissioning in July, 2021.

Contact Us

Tel:+86-25-84152563

Fax:+86-25-52146294

Email:export@hbtianrui.com

Address:Head Office: No.8 Chuangye Avenue, Economic Development Zone, Tianmen City, Hubei Province, China (Zip Code: 431700) Nanjing Office: Building 23, Baijiahu Science and Technology Industrial Park, No.2 Qingshuiting West Road, Jiangning Economic Development Zone, Nanjing City, Jiangsu Province,China (Zip Code:211106)

Thank you for your message. We will contact you as soon as possible!