Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest

from:China Three Gorges Corporationdate:2019-11-11

Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest-1

Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest on the left bank on November 3.

The first seat ring was shipped to the site and began assembly on September 15, 2018. It was hoisted into the nest on November 24, 2018. The last seat ring started assembly on September 6, 2019 and welding on September 11.

A total of 8 seat rings for the left bank completed assembly and welding within 16 months, laying a solid ground to make it an excellent mechanical and electric project.

Contact Us

Tel:+86-25-84152563

Fax:+86-25-52146294

Email:export@hbtianrui.com

Address:Head Office: No.8 Chuangye Avenue, Economic Development Zone, Tianmen City, Hubei Province, China (Zip Code: 431700) Nanjing Office: Building 23, Baijiahu Science and Technology Industrial Park, No.2 Qingshuiting West Road, Jiangning Economic Development Zone, Nanjing City, Jiangsu Province,China (Zip Code:211106)

Thank you for your message. We will contact you as soon as possible!